Lawn irrigation systems: Usually
done at the counter, but may take up to two days.
Swimming pools and fences: Usually takes
3 - 5 business days. After the permit request has been reviewed,
the applicant will be contacted and informed if the permit
has been approved -- or if changes must be made to the submittal
request.
New commercial building or addition: Approximately
20 working days. After the permit request has been reviewed,
the applicant will be contacted and informed if the permit
has been approved -- or if changes must be made to the submittal
request. Revised plans are normally reviewed within a week
of receiving the revisions.
Commercial remodel: Approximately 15 working
days. After the permit request has been reviewed, the applicant
will be contacted and informed if the permit has been approved
-- or if changes must be made to the submittal request.
Sign Permits: Approximately 5 working days.
After the permit request has been reviewed, the applicant
will be contacted and informed if the permit has been approved
-- or if changes must be made to the submittal request.